Person in dark setting, thoughtful expression.
GCC REGION

KAIROS INSIGHT · Construction Claims Management 

Most programmes give away money they are owed

Why weak construction claims management leaves commercial value uncaptured on complex capital programmes

This Insight Covers

  • What most projects lose to poor claims management is not a dispute they should have won, but entitlement they never assembled the evidence to claim.
  • Why value leaks is rarely the absence of grounds, but the absence of records, timely notices, and disciplined substantiation to support them.
  • How strong claims management works is as a continuous commercial function running through delivery, not a defensive scramble mounted at close-out.
  • When entitlement is secured or surrendered is during the works, in the daily record, long before any formal claim is drafted.
  • Who leaves the most on the table are the programmes that treat claims as an adversarial last resort rather than a routine part of managing change.

~12 min read

On most complex capital programmes, a significant amount of money that one party is entitled to recover is never recovered. The entitlement is real. The grounds exist. The change happened, the delay was caused, the disruption was suffered. And yet, when the final account is settled, a large part of that value has quietly evaporated. It was not lost in a dispute that went the wrong way. It was surrendered, long before any dispute, through the slow failure to build the case for it while the evidence was still there to be gathered. This is the central problem of construction claims management, and it is more common than the industry likes to admit.

Construction Claims Management
Why weak construction claims management leaves commercial value uncaptured on complex capital programmes 4

Claims management is often confused with disputes, litigation, and the adversarial end of a project. That confusion is part of the problem. A claim, in its proper sense, is nothing more than a structured request for the time or money a contract entitles a party to when circumstances change. On a programme issuing hundreds of variations and absorbing dozens of delay events, claims are not exceptional. They are the ordinary mechanism by which the commercial position keeps pace with what is actually happening on site. Managing them well is a routine discipline of delivery, not a sign that something has gone wrong.

The GCC market makes this discipline both harder and more valuable. Regional programmes tend to run at pace, with fixed completion dates tied to public commitments, and they frequently use heavily amended standard forms in which notice requirements and time bars are strict and unforgiving. Scope changes late and often. Design information arrives incomplete. Approvals lag. Each of these is a legitimate source of entitlement, and each one is also a test of whether the team can capture that entitlement before the window to do so closes. When the discipline is weak, the value leaks away in exactly the conditions that should have produced the strongest claims.

What separates the programmes that recover what they are owed from those that do not is not luck, and it is not the strength of their contracts. It is whether they treat claims management as a continuous commercial function or as a defensive exercise mounted too late. The difference is worth a great deal of money.

Claims management does not begin when a claim is submitted. It begins the day the works start, in the records that will one day either prove an entitlement or quietly fail to.

01  ·  Claims management

Claims management is a commercial discipline, not a dispute

The most damaging misconception on a capital programme is that raising a claim is an act of aggression. Teams delay notifying entitlement because they do not want to sour the relationship, or because they assume the matter can be sorted out later in a spirit of goodwill. Later rarely arrives on favourable terms. By the time the final account is in view, positions have hardened, personnel have moved on, and the goodwill that was supposed to resolve everything has been spent on the last three disagreements. The entitlement that could have been secured cleanly, at the time, becomes a contested line item argued from memory.

Treating claims as a normal part of managing change removes that dynamic. When notice and substantiation are routine, expected, and handled without drama, they stop being provocations and become administration. The best-run programmes normalise the process so thoroughly that a notice of delay is no more adversarial than a progress report. That cultural shift, from claims as conflict to claims as commercial hygiene, is often the single largest lever available to an owner or contractor trying to protect their position.

The discipline cuts both ways, which is often overlooked. An owner or its consultant receiving a claim has the same interest in rigour as the party making one. A claim that is properly assessed, on its contractual merits and against the evidence, can be settled at its correct value rather than paid in full to avoid argument or rejected wholesale and left to fester into a dispute. Weak claims management on the receiving side is as costly as weak claims management on the submitting side. It leads to over-payment where a claim should have been challenged, and to escalation where a valid claim should have been agreed. The discipline that lets a party build a strong claim is the same discipline that lets it evaluate one fairly, and the programmes that hold both sides of that capability are the ones that keep their commercial position under control.

02  ·  Built in the record

Entitlement is built in the record, not recovered in the negotiation

Every claim rests on evidence, and that evidence is created or lost during the works, not at the point the claim is made. The programme, the progress records, the correspondence, the site diaries, the measurements: these are the raw material from which entitlement is assembled. A team that maintains them rigorously has a case ready to be stated. A team that does not is left trying to reconstruct what happened months or years after the fact, from incomplete files and fading recollection, against a counterparty with every incentive to dispute the gaps.

Nowhere is this clearer than in delay. The programme is the instrument through which delay is proved, and a programme that is not properly maintained cannot support a claim for an extension of time. The Kairos insight on construction schedule management makes the point that the schedule is not merely a planning tool but the evidentiary backbone of every time-related entitlement, and that programmes left un-updated through the works forfeit their value precisely when they are needed most. The internationally recognised SCL Delay and Disruption Protocol rests on the same principle: it treats a properly maintained programme and an agreed record-keeping regime as the foundation of any defensible delay or disruption claim, and it discourages the “wait and see” approach in which parties defer assessing entitlement until the damage is done and the evidence has gone cold.

03  ·  Entitlement

Notice is where entitlement is preserved or forfeited

Most standard forms, and almost all heavily amended regional ones, make entitlement conditional on notice. A valid claim served late, or not served at all, can be barred regardless of its underlying merit. This is the harshest and least forgiving part of claims management, and it is where value is most often lost outright rather than merely eroded. A contractor with a strong delay claim who misses a fourteen-day or twenty-eight-day notice provision may lose the entire entitlement, not because the delay was not real, but because the contractual precondition to claiming it was not met.

Managing notice is unspectacular and relentless. It means knowing every notice obligation across every package, tracking the events that trigger them, and serving on time, every time, without waiting for certainty about the full impact. The discipline fails not through incompetence but through inattention, when the team is absorbed in building and no one owns the calendar of contractual deadlines. On a programme where a single missed notice can extinguish a seven-figure entitlement, that ownership is not optional.

A valid entitlement with no contemporaneous record behind it is worth very little. An ordinary entitlement with a clean record and timely notice behind it is worth almost all of it.

04  ·  Most expensive claims

Unsubstantiated claims are the most expensive claims

When claims are finally made, they are often made badly, and a badly made claim costs more than no claim at all. It consumes time and professional fees, invites rejection, sours the relationship, and frequently recovers a fraction of what a well-prepared claim would have secured. Arcadis, in its 2025 Global Construction Disputes Report tracks a sustained rise in the average value of construction disputes, and its research has consistently found that poorly drafted, incomplete, or unsubstantiated claims rank among the leading causes of disputes worldwide. The pattern is telling. The problem is frequently not the absence of entitlement but the failure to present it in a form the other party can assess and accept.

A well-substantiated claim does the opposite. It states the contractual basis clearly, links cause to effect with contemporaneous evidence, and quantifies the consequence in a way that can be checked. It gives the receiving party a reason to agree rather than a reason to resist. This is a skill, and a scarce one, combining contractual knowledge, forensic discipline, and the ability to tell a clear factual story. Programmes that invest in that capability recover more, recover faster, and do less damage to the relationships they depend on to finish the work.

Timing matters as much as quality. A claim assessed and agreed close to the event that gave rise to it is far cheaper to resolve than one bundled into a contested final account two years later. Dealing with entitlement as it arises keeps the sums small, the facts fresh, and the relationship workable, and it prevents the accumulation of unresolved items that eventually hardens into a single, expensive dispute. The programmes that resolve claims continuously rather than deferring them almost always finish in a stronger commercial position than those that let entitlement pile up unaddressed until the end.

05  ·  Risks

The risks that become claims are visible early

The events that generate the largest claims are rarely surprises. Scope uncertainty, incomplete design, constrained access, delayed approvals, and interface conflicts between packages are visible as risks long before they crystallise into entitlement. A programme that tracks those risks actively is a programme that can see its future claims forming and begin building the record for them in advance, rather than discovering the need for evidence after the moment to capture it has passed. The Kairos insight on risk register in project management explores how disciplined risk tracking turns a reactive register into a forward-looking management tool, and the same logic applies directly to claims: the risk that is being monitored is the claim that will be properly documented.

This connection between risk and claims is under-exploited on most programmes. Risk management and commercial management are often run as separate activities, by separate people, on separate systems. Joining them means that when a monitored risk materialises, the contractual and evidential response is already prepared rather than improvised. It converts risk awareness into commercial protection, which is what risk management is meant to deliver in the first place.

06  ·  Construction claims management

What good construction claims management looks like on a GCC programme

Construction Claims Management
Why weak construction claims management leaves commercial value uncaptured on complex capital programmes 5

Brought together, strong claims management on a complex regional programme is recognisable by its ordinariness. Notices are served on time as a matter of routine. Records are maintained to a standard that would withstand scrutiny, whether or not a claim is ever made. The programme is kept live and used as the instrument it is meant to be. Risks are tracked in a way that anticipates the claims they may become. And when a claim is made, it is substantiated to a standard that invites agreement rather than resistance. None of this is dramatic. All of it is disciplined.

The return on that discipline is asymmetric. The cost of maintaining good records and serving timely notices is modest and predictable. The cost of failing to is a large and unpredictable loss at the point it hurts most, when the programme is trying to close out and the value that should have been recovered has evaporated. Owners and contractors alike tend to under-invest in claims management precisely because its benefit is invisible when it is working, revealed only in the losses it quietly prevents. That invisibility is what makes it so easy to neglect and so valuable to get right.

Conclusion: The value was always there

The money that most programmes leave on the table was never out of reach. The entitlement existed, the grounds were sound, and the contract provided the mechanism to recover it. What was missing was the discipline to capture it while it could still be captured: the notice served in time, the record kept when nothing seemed to depend on it, the claim built carefully rather than assembled in a panic at the end. Construction claims management is the function that turns entitlement a party holds in principle into value it actually recovers. On a complex capital programme, the gap between what is owed and what is collected is one of the largest and most avoidable losses in the whole enterprise, and closing it is almost entirely a matter of doing ordinary things consistently, from the first day of the works to the last.

WORK WITH KAIROS

If your programme is in distress, we can help.

Kairos provides construction claims management support for complex capital programmes across the GCC, spanning notice and obligation tracking, records and programme discipline, delay and disruption analysis, and the preparation of substantiated claims that hold up to scrutiny. We help owners and delivery teams capture the entitlement they are owed before the window to prove it closes. To discuss how disciplined claims management can protect the value in your programme.